{"schemaVersion":"1.0","canonicalUrl":"https://northcarolinai.com/data-centers/eco-tip-west-chatham","packetUrl":"https://northcarolinai.com/diligence/eco-tip-west-chatham","reviewDate":"2026-11-18","project":{"slug":"eco-tip-west-chatham","name":"Eco TIP West site, Chatham County","operator":"Eco TIP West LLC","location":"Near Pea Ridge Road and Old US 1, TIP West","locality":"Chatham County","region":"triangle","kind":"campus","status":"Court order filed September 18, 2026 — later disposition unverified","confidence":"B","summary":"A Chatham County Superior Court order identifies Eco TIP West’s TIP West property near Pea Ridge Road and Old US 1 and records a September 2026 ruling in its dispute with the county.","details":["The order in case 26CV000456-180 identifies plaintiff-owned property in Chatham County near Pea Ridge Road and Old US 1, known as TIP West. The document is a copy of the court order, with the filed stamp and judicial signature visible. [eco-tip-west-court-order-2026-09-18]","Judge John M. Morris signed the order on September 17, 2026; the filed stamp is September 18, 2026. The order grants summary judgment on liability and attorneys’ fees and reserves damages for further proceedings. [eco-tip-west-court-order-2026-09-18]","The court order supplies a historical legal milestone. The reviewed order does not establish megawatt capacity, construction completion, utility delivery, or the later appeal or final damages outcome. [eco-tip-west-court-order-2026-09-18]"],"sourceIds":["census-counties","eco-tip-west-court-order-2026-09-18"],"capex":"Site capital expenditure not verified in reviewed primary documents","power":"Utility or IT capacity not verified in reviewed primary documents","jobs":"Site employment not verified in reviewed primary documents","verifiedAt":"2026-11-18","lat":35.704994,"lng":-79.251454,"approximateLocation":true,"locationNote":"Approximate Chatham County Census Gazetteer internal point; not the campus location or parcel boundary."},"sources":[{"id":"census-counties","title":"2025 Census Gazetteer county internal points","url":"https://www2.census.gov/geo/docs/maps-data/data/gazetteer/2025_Gazetteer/2025_Gaz_counties_national.zip","publisher":"U.S. Census Bureau","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"eco-tip-west-court-order-2026-09-18","title":"Eco TIP West v. Chatham County court order, filed September 18, 2026","url":"https://www.carolinajournal.com/wp-content/uploads/2026/09/chatham-data-center-091726.pdf","publisher":"North Carolina Superior Court, Chatham County (court-order copy hosted by Carolina Journal)","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}],"qualifications":["This is a public research packet, not a legal, tax, engineering or investment opinion.","A source association is not proof of a final permit, utility commitment, incentive award or completed project.","Campus and multi-site program scopes are different. Do not sum overlapping program and campus investment or capacity figures.","Publication dates, desk review dates and project milestones have different meanings. An export is not a new source verification.","Unknown or undisclosed values remain unknown; locality markers are approximate and do not establish parcel jurisdiction."],"openQuestions":[{"topic":"Land use and jurisdiction","question":"Which parcel, legal jurisdiction and land-use approvals apply to Eco TIP West site, Chatham County?","boundary":"The reviewed locality label is “Chatham County”. Confirm parcel jurisdiction independently. No locality-matched land-use reference is recorded in this packet; consult the actual governing jurisdiction.","references":[]},{"topic":"Electric service","question":"What site-specific utility service agreement, interconnection milestone and delivery date are documented?","boundary":"Reviewed disclosure: Utility or IT capacity not verified in reviewed primary documents. A campus specification is not an energized utility commitment. The general utility and Commission references do not identify the serving utility, governing rate or service agreement for this particular site.","references":[{"id":"duke-large-load","url":"https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs","title":"Duke Energy proposed data-center cost safeguards","publisher":"Duke Energy","accessedAt":"2026-10-30","verifiedAt":"2026-10-30"},{"id":"duke-ncuc-orders-8k","title":"Form 8-K: NCUC written orders in Duke Energy Carolinas and Duke Energy Progress 2025 rate cases","url":"https://www.sec.gov/Archives/edgar/data/17797/000110465926128747/tm2629986d1_8k.htm","publisher":"Duke Energy Corporation (SEC Form 8-K)","verifiedAt":"2026-11-17","accessedAt":"2026-11-17","publishedAt":"2026-11-17"},{"id":"ncuc","url":"https://www.ncuc.gov/","title":"North Carolina Utilities Commission","publisher":"North Carolina Utilities Commission","accessedAt":"2026-10-30","verifiedAt":"2026-10-30"}]},{"topic":"Environmental and water review","question":"Which air, water and cooling records apply to the actual site and phase?","boundary":"The register does not establish a project-specific water allocation or final environmental approval.","references":[{"id":"ncdeq-air","title":"Air Quality Permitting","url":"https://www.deq.nc.gov/about/divisions/air-quality/air-quality-permitting","publisher":"N.C. Department of Environmental Quality","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"ncdeq-water","title":"Water Quality Permitting","url":"https://www.deq.nc.gov/about/divisions/water-resources/water-quality-permitting","publisher":"N.C. Department of Environmental Quality","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}]},{"topic":"Investment and incentives","question":"Which site-specific investment scope and written incentive or tax-qualification records are available?","boundary":"Reviewed investment disclosure: Site capital expenditure not verified in reviewed primary documents. A program commitment is not a campus valuation.","references":[{"id":"ncdor-data-centers","url":"https://www.ncdor.gov/taxes-forms/sales-and-use-tax/other-sales-and-use-tax-resources/important-notices-issued-sales-and-use-tax-division/important-notice-repeal-exemptions-electricity-used-datacenters","title":"Repeal of electricity exemptions for datacenters","publisher":"N.C. Department of Revenue","accessedAt":"2026-10-30","verifiedAt":"2026-10-30","publishedAt":"2026-07-23"}]},{"topic":"Employment and timing","question":"Which phase, hiring dates, job types and current employer postings are documented?","boundary":"Reviewed jobs disclosure: Site employment not verified in reviewed primary documents. An announced target is not a live vacancy count. The operator references do not establish an employer affiliation, hiring commitment or project-specific training agreement for an unrelated training provider.","references":[{"id":"census-counties","title":"2025 Census Gazetteer county internal points","url":"https://www2.census.gov/geo/docs/maps-data/data/gazetteer/2025_Gazetteer/2025_Gaz_counties_national.zip","publisher":"U.S. Census Bureau","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"eco-tip-west-court-order-2026-09-18","title":"Eco TIP West v. Chatham County court order, filed September 18, 2026","url":"https://www.carolinajournal.com/wp-content/uploads/2026/09/chatham-data-center-091726.pdf","publisher":"North Carolina Superior Court, Chatham County (court-order copy hosted by Carolina Journal)","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}]}]}