{"schemaVersion":"1.0","canonicalUrl":"https://northcarolinai.com/data-centers/microsoft-person-county","packetUrl":"https://northcarolinai.com/diligence/microsoft-person-county","reviewDate":"2026-11-18","project":{"slug":"microsoft-person-county","name":"Microsoft Person County datacenter campus","operator":"Microsoft","location":"Person County","locality":"Person County","region":"triangle","kind":"campus","status":"Planning — early site preparation (operator update, April 2026)","confidence":"B","summary":"Microsoft bought 1,350 acres in Person County in October 2024 and plans a datacenter campus there. Its April 2026 update says the project is in planning, with early site preparation under way.","details":["Person County’s February 24, 2026 release says Microsoft planned to begin the permitting process later that year and is in the early stages of development; this record has not verified a permit application. [person-county-microsoft-2026-02-24]","Microsoft’s update mentions soil sampling, surveying and road work for the permanent closure of Country Club Road, and says the datacenters are expected to use air-cooled chillers on a closed, recirculating water loop. No capacity, investment or job figure is given. [microsoft-person-county]"],"capex":"Not disclosed in cited source","power":"Not disclosed in cited source","jobs":"Not disclosed in cited source","sourceIds":["census-counties","person-county-microsoft-2026-02-24","microsoft-person-county","microsoft-local-nc"],"verifiedAt":"2026-11-18","lat":36.388308,"lng":-78.973717,"approximateLocation":true,"locationNote":"Approximate Person County Census Gazetteer internal point; not the campus location or parcel boundary."},"sources":[{"id":"census-counties","title":"2025 Census Gazetteer county internal points","url":"https://www2.census.gov/geo/docs/maps-data/data/gazetteer/2025_Gazetteer/2025_Gaz_counties_national.zip","publisher":"U.S. Census Bureau","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"person-county-microsoft-2026-02-24","title":"INDUSTRY ALERT: Microsoft Shares Update for Person County","url":"https://www.personcountync.gov/Home/Components/News/News/3962/33","publisher":"Person County","publishedAt":"2026-02-24","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"microsoft-person-county","title":"Person County datacenter project","url":"https://local.microsoft.com/blog/person-county-datacenter-project/","publisher":"Microsoft","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"microsoft-local-nc","title":"Microsoft in your community: North Carolina","url":"https://local.microsoft.com/communities/americas/north-carolina/","publisher":"Microsoft","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}],"qualifications":["This is a public research packet, not a legal, tax, engineering or investment opinion.","A source association is not proof of a final permit, utility commitment, incentive award or completed project.","Campus and multi-site program scopes are different. Do not sum overlapping program and campus investment or capacity figures.","Publication dates, desk review dates and project milestones have different meanings. An export is not a new source verification.","Unknown or undisclosed values remain unknown; locality markers are approximate and do not establish parcel jurisdiction."],"openQuestions":[{"topic":"Land use and jurisdiction","question":"Which parcel, legal jurisdiction and land-use approvals apply to Microsoft Person County datacenter campus?","boundary":"The reviewed locality label is “Person County”. Confirm parcel jurisdiction independently. No locality-matched land-use reference is recorded in this packet; consult the actual governing jurisdiction.","references":[]},{"topic":"Electric service","question":"What site-specific utility service agreement, interconnection milestone and delivery date are documented?","boundary":"Reviewed disclosure: Not disclosed in cited source. A campus specification is not an energized utility commitment. The general utility and Commission references do not identify the serving utility, governing rate or service agreement for this particular site.","references":[{"id":"duke-large-load","url":"https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs","title":"Duke Energy proposed data-center cost safeguards","publisher":"Duke Energy","accessedAt":"2026-10-30","verifiedAt":"2026-10-30"},{"id":"duke-ncuc-orders-8k","title":"Form 8-K: NCUC written orders in Duke Energy Carolinas and Duke Energy Progress 2025 rate cases","url":"https://www.sec.gov/Archives/edgar/data/17797/000110465926128747/tm2629986d1_8k.htm","publisher":"Duke Energy Corporation (SEC Form 8-K)","verifiedAt":"2026-11-17","accessedAt":"2026-11-17","publishedAt":"2026-11-17"},{"id":"ncuc","url":"https://www.ncuc.gov/","title":"North Carolina Utilities Commission","publisher":"North Carolina Utilities Commission","accessedAt":"2026-10-30","verifiedAt":"2026-10-30"}]},{"topic":"Environmental and water review","question":"Which air, water and cooling records apply to the actual site and phase?","boundary":"The register does not establish a project-specific water allocation or final environmental approval.","references":[{"id":"ncdeq-air","title":"Air Quality Permitting","url":"https://www.deq.nc.gov/about/divisions/air-quality/air-quality-permitting","publisher":"N.C. Department of Environmental Quality","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"ncdeq-water","title":"Water Quality Permitting","url":"https://www.deq.nc.gov/about/divisions/water-resources/water-quality-permitting","publisher":"N.C. Department of Environmental Quality","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}]},{"topic":"Investment and incentives","question":"Which site-specific investment scope and written incentive or tax-qualification records are available?","boundary":"Reviewed investment disclosure: Not disclosed in cited source. A program commitment is not a campus valuation.","references":[{"id":"ncdor-data-centers","url":"https://www.ncdor.gov/taxes-forms/sales-and-use-tax/other-sales-and-use-tax-resources/important-notices-issued-sales-and-use-tax-division/important-notice-repeal-exemptions-electricity-used-datacenters","title":"Repeal of electricity exemptions for datacenters","publisher":"N.C. Department of Revenue","accessedAt":"2026-10-30","verifiedAt":"2026-10-30","publishedAt":"2026-07-23"}]},{"topic":"Employment and timing","question":"Which phase, hiring dates, job types and current employer postings are documented?","boundary":"Reviewed jobs disclosure: Not disclosed in cited source. An announced target is not a live vacancy count. The operator references do not establish an employer affiliation, hiring commitment or project-specific training agreement for an unrelated training provider.","references":[{"id":"census-counties","title":"2025 Census Gazetteer county internal points","url":"https://www2.census.gov/geo/docs/maps-data/data/gazetteer/2025_Gazetteer/2025_Gaz_counties_national.zip","publisher":"U.S. Census Bureau","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"person-county-microsoft-2026-02-24","title":"INDUSTRY ALERT: Microsoft Shares Update for Person County","url":"https://www.personcountync.gov/Home/Components/News/News/3962/33","publisher":"Person County","publishedAt":"2026-02-24","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"microsoft-person-county","title":"Person County datacenter project","url":"https://local.microsoft.com/blog/person-county-datacenter-project/","publisher":"Microsoft","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"microsoft-local-nc","title":"Microsoft in your community: North Carolina","url":"https://local.microsoft.com/communities/americas/north-carolina/","publisher":"Microsoft","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}]}]}