{"schemaVersion":"1.0","canonicalUrl":"https://northcarolinai.com/data-centers/t5-charlotte-enterprise-park","packetUrl":"https://northcarolinai.com/diligence/t5-charlotte-enterprise-park","reviewDate":"2026-11-18","project":{"slug":"t5-charlotte-enterprise-park","name":"T5 Charlotte enterprise data-center park","operator":"T5 Data Centers","location":"Countryside Road, Kings Mountain","locality":"Cleveland County","region":"charlotte","kind":"program","status":"Existing enterprise data-center park — city-described scope","confidence":"B","summary":"Kings Mountain describes existing smaller cloud and enterprise facilities in T5 Data Center Park and along Countryside Road. This record covers the park scope rather than counting each internal facility as a separate campus.","details":["The current city explanation identifies existing smaller cloud and enterprise facilities in T5 Data Center Park and along Countryside Road. It states that Kings Mountain currently has no hyperscale, AI-training, or neocloud data centers. [kings-mountain-data-centers]","Cleveland County’s February 21, 2012 commissioners minutes identify T5 Data Center Park on Countryside Road and discuss county infrastructure and incentives, establishing the Cleveland County jurisdiction. [cleveland-t5-minutes-2012]","An operator sheet describes a 300-acre enterprise park, four existing operations, three build-to-suit pads and an on-site Duke substation. Its printed publication date is not recorded, and these sheet specifications are kept separate from current available service or IT load. [t5-charlotte-operator-sheet]"],"sourceIds":["census-counties","t5-charlotte-operator-sheet","kings-mountain-data-centers","cleveland-t5-minutes-2012"],"capex":"Park/program amount not separately disclosed in this review","power":"Current utility or IT service not verified at park scope","jobs":"Park employment not verified in reviewed primary sources","verifiedAt":"2026-11-18"},"sources":[{"id":"census-counties","title":"2025 Census Gazetteer county internal points","url":"https://www2.census.gov/geo/docs/maps-data/data/gazetteer/2025_Gazetteer/2025_Gaz_counties_national.zip","publisher":"U.S. Census Bureau","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"t5-charlotte-operator-sheet","title":"T5 Charlotte data-center park operator sheet","url":"https://t5datacenters.com/wp-content/uploads/2018/12/T5_Charlotte_Flyer_20210907.pdf","publisher":"T5 Data Centers","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"kings-mountain-data-centers","title":"Understanding Data Centers in Kings Mountain","url":"https://www.cityofkm.com/842/Understanding-Data-Centers","publisher":"City of Kings Mountain","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"cleveland-t5-minutes-2012","title":"Cleveland County commissioners minutes, February 21, 2012","url":"https://www.clevelandcounty.com/main/Document%20Center/Agendas%20and%20Minutes/BOARD%20OF%20COUNTY%20COMMISSIONERS/2012/minutes02212012b.pdf","publisher":"Cleveland County","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}],"qualifications":["This is a public research packet, not a legal, tax, engineering or investment opinion.","A source association is not proof of a final permit, utility commitment, incentive award or completed project.","Campus and multi-site program scopes are different. Do not sum overlapping program and campus investment or capacity figures.","Publication dates, desk review dates and project milestones have different meanings. An export is not a new source verification.","Unknown or undisclosed values remain unknown; locality markers are approximate and do not establish parcel jurisdiction."],"openQuestions":[{"topic":"Land use and jurisdiction","question":"Which parcel, legal jurisdiction and land-use approvals apply to T5 Charlotte enterprise data-center park?","boundary":"The register describes a multi-site program; no single campus approval is implied. No locality-matched land-use reference is recorded in this packet; consult the actual governing jurisdiction.","references":[]},{"topic":"Electric service","question":"What site-specific utility service agreement, interconnection milestone and delivery date are documented?","boundary":"Reviewed disclosure: Current utility or IT service not verified at park scope. A campus specification is not an energized utility commitment. The general utility and Commission references do not identify the serving utility, governing rate or service agreement for this particular site.","references":[{"id":"duke-large-load","url":"https://news.duke-energy.com/releases/duke-energy-protects-customers-from-data-center-costs","title":"Duke Energy proposed data-center cost safeguards","publisher":"Duke Energy","accessedAt":"2026-10-30","verifiedAt":"2026-10-30"},{"id":"duke-ncuc-orders-8k","title":"Form 8-K: NCUC written orders in Duke Energy Carolinas and Duke Energy Progress 2025 rate cases","url":"https://www.sec.gov/Archives/edgar/data/17797/000110465926128747/tm2629986d1_8k.htm","publisher":"Duke Energy Corporation (SEC Form 8-K)","verifiedAt":"2026-11-17","accessedAt":"2026-11-17","publishedAt":"2026-11-17"},{"id":"ncuc","url":"https://www.ncuc.gov/","title":"North Carolina Utilities Commission","publisher":"North Carolina Utilities Commission","accessedAt":"2026-10-30","verifiedAt":"2026-10-30"}]},{"topic":"Environmental and water review","question":"Which air, water and cooling records apply to the actual site and phase?","boundary":"The register does not establish a project-specific water allocation or final environmental approval.","references":[{"id":"ncdeq-air","title":"Air Quality Permitting","url":"https://www.deq.nc.gov/about/divisions/air-quality/air-quality-permitting","publisher":"N.C. Department of Environmental Quality","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"ncdeq-water","title":"Water Quality Permitting","url":"https://www.deq.nc.gov/about/divisions/water-resources/water-quality-permitting","publisher":"N.C. Department of Environmental Quality","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}]},{"topic":"Investment and incentives","question":"Which site-specific investment scope and written incentive or tax-qualification records are available?","boundary":"Reviewed investment disclosure: Park/program amount not separately disclosed in this review. A program commitment is not a campus valuation.","references":[{"id":"ncdor-data-centers","url":"https://www.ncdor.gov/taxes-forms/sales-and-use-tax/other-sales-and-use-tax-resources/important-notices-issued-sales-and-use-tax-division/important-notice-repeal-exemptions-electricity-used-datacenters","title":"Repeal of electricity exemptions for datacenters","publisher":"N.C. Department of Revenue","accessedAt":"2026-10-30","verifiedAt":"2026-10-30","publishedAt":"2026-07-23"}]},{"topic":"Employment and timing","question":"Which phase, hiring dates, job types and current employer postings are documented?","boundary":"Reviewed jobs disclosure: Park employment not verified in reviewed primary sources. An announced target is not a live vacancy count. The operator references do not establish an employer affiliation, hiring commitment or project-specific training agreement for an unrelated training provider.","references":[{"id":"census-counties","title":"2025 Census Gazetteer county internal points","url":"https://www2.census.gov/geo/docs/maps-data/data/gazetteer/2025_Gazetteer/2025_Gaz_counties_national.zip","publisher":"U.S. Census Bureau","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"t5-charlotte-operator-sheet","title":"T5 Charlotte data-center park operator sheet","url":"https://t5datacenters.com/wp-content/uploads/2018/12/T5_Charlotte_Flyer_20210907.pdf","publisher":"T5 Data Centers","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"kings-mountain-data-centers","title":"Understanding Data Centers in Kings Mountain","url":"https://www.cityofkm.com/842/Understanding-Data-Centers","publisher":"City of Kings Mountain","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"},{"id":"cleveland-t5-minutes-2012","title":"Cleveland County commissioners minutes, February 21, 2012","url":"https://www.clevelandcounty.com/main/Document%20Center/Agendas%20and%20Minutes/BOARD%20OF%20COUNTY%20COMMISSIONERS/2012/minutes02212012b.pdf","publisher":"Cleveland County","verifiedAt":"2026-11-18","accessedAt":"2026-11-18"}]}]}