A moratorium is a temporary pause, not a ban
Desk analysisCharlotte’s FAQ describes a moratorium as a temporary pause imposed by local government on issuing new development approvals, such as zoning or building permits, for a set period; it says a moratorium does not halt approved development projects or adopted rezonings, and that existing data centers may continue operating. [City of Charlotte]
The Statesville and Vance County records cite N.C.G.S. 160D-107, the state statute on development moratoria. Kings Mountain’s staff told the City Council that moratoriums are not permanent, cannot be excessive and can only be implemented for a specific purpose, and that its moratorium would not apply to developments with a valid permit, a site-specific vesting plan or a development agreement. [City of Statesville; Vance County Clerk to the Board; City of Kings Mountain]
Our analysis: read each moratorium for four things, in this order: the body that adopted it and the date of the vote; the territory it covers (county zoning jurisdiction, city limits, extraterritorial jurisdiction or planning area); the approvals it pauses and the projects it exempts; and the end date, including any earlier end tied to adopting new standards. A moratorium in one town says nothing about the surrounding county unless its own text says so.
County boards of commissioners
Each entry below is the summary shown on that county’s page in this register, with the primary record it rests on. County moratoriums generally apply within the county’s own zoning jurisdiction; a city inside the county regulates its own territory.
Chatham County: On February 11, 2026, the Board of Commissioners adopted a temporary moratorium on data-center approvals. [Chatham County Planning]
Cumberland County: The County’s official data-center page records Board approval of a six-month moratorium on June 15, 2026; the same page states that a proposed permanent data-center ordinance remains under review and has not been adopted. [Cumberland County Planning and Inspections]
Surry County: On July 20, 2026, the Board of Commissioners extended the temporary moratorium on data-center development approvals, first approved June 1, 2026. It expires July 20, 2028. [Surry County Development Services]
Davie County: On July 6, 2026, the Board of Commissioners adopted a one-year moratorium on data-center development, commencing July 6, 2026 and expiring no later than July 5, 2027. [Davie County Board of Commissioners]
Edgecombe County: The minutes of the August 3, 2026 Board meeting, presented for approval in the September 8 agenda packet, record that the Board adopted a two-year moratorium on development applications and permits for data centers and related uses in the county’s zoning jurisdiction. A timeline in the same packet dates the adoption August 6, 2026. [Edgecombe County Board of Commissioners]
Alamance County: On August 17, 2026, the Board of Commissioners adopted a temporary moratorium on new Large-Scale Data Centers (10 MW or more aggregate maximum electric demand) and expansions of existing ones; the ordinance expires at 11:59 p.m. on February 17, 2027. [Alamance County Board of Commissioners]
Yadkin County: On August 17, 2026, the Board of Commissioners adopted a twenty-four-month temporary moratorium on permitting of data centers, data processing facilities, cryptocurrency mining, and similar uses in unincorporated Yadkin County; it expires no later than August 17, 2028, or upon approval of new zoning regulations, whichever is earlier. [Yadkin County Board of Commissioners]
Jackson County: The moratorium ordinance (O2026-02) in the Board of Commissioners’ agenda packet runs from August 18, 2026 to no later than August 18, 2027. The posted copy is unsigned. [Jackson County Board of Commissioners]
Durham County: On August 24, 2026, the Board of County Commissioners approved a nine-month moratorium prohibiting new data centers and expansions beyond 100,000 total square feet; smaller enterprise and edge facilities below that size remain exempt. [Durham County]
Nash County: On September 8, 2026, the Board of Commissioners adopted a temporary development moratorium on data centers, data processing facilities, cryptocurrency mining operations, and similar uses in unincorporated Nash County; it expires June 30, 2027, or upon approval of new zoning regulations addressing those uses, whichever is earlier. [Nash County Board of Commissioners]
Vance County: On September 14, 2026, the Board of Commissioners voted 5-2 to approve a 60-day moratorium ordinance on data-center development applications submitted after its adoption; the minutes describe its term as the sooner of 60 days or adoption of a data-center text amendment. [Vance County Board of Commissioners]
Vance County: A November 6, 2026 notice called a November 13, 2026 special meeting to consider extending the moratorium, then scheduled to expire November 13, by thirty days through December 13, 2026. This register has not seen a county record of the outcome. [Vance County Clerk to the Board]
Beaufort County: The October 5, 2026 Board agenda packet includes an ordinance establishing a temporary one-year moratorium on acceptance, processing, and approval of data-center applications in unincorporated Beaufort County; Section 5 states a duration of September 14, 2026 through September 14, 2027. [Beaufort County Board of Commissioners]
Beaufort County: The November 2, 2026 Board agenda states that the Board voted to approve the Data Center Moratorium. [Beaufort County Board of Commissioners]
Guilford County: Guilford County’s Legistar record for file 2026-452, the November 5, 2026 hearing on a temporary moratorium on development approvals for new data centers in unincorporated Guilford County, lists its status as Passed with final action on November 5, 2026. This register has not seen the adopted ordinance text or its end date. [Guilford County Board of Commissioners]
Pitt County: The November 16, 2026 Board of Commissioners agenda listed a public hearing to consider adoption of a moratorium on data processing facilities (data centers). This register has not seen a county record of the outcome. [Pitt County Board of Commissioners]
Pasquotank County: The November 16, 2026 Board of Commissioners agenda listed a public hearing on a proposed ordinance instituting a temporary moratorium on permitting data centers, data processing facilities, cryptocurrency mining operations and associated uses. This register has not seen a county record of the outcome. [Pasquotank County Board of Commissioners]
Chowan County: The county posted a draft ordinance for its November 23, 2026 public hearing that would pause development approvals for data centers, cryptocurrency mining and other high-impact data processing facilities in unincorporated Chowan County from November 23, 2026 until November 23, 2027. The posted copy is an unsigned draft; this register has not seen a county record of the vote. [Chowan County Board of Commissioners]
Cities and towns
Municipal moratoriums cover the city or town and, where the record says so, its extraterritorial jurisdiction. They are listed with the county page that carries them.
Kings Mountain: On February 24, 2026, Kings Mountain City Council adopted Ordinance 26-11, a 182-day moratorium on permitting new data centers, by a 5-2 vote; it does not apply to developments with a valid permit, a site-specific vesting plan or a development agreement. [City of Kings Mountain]
Kings Mountain: On August 25, 2026, Kings Mountain City Council adopted Ordinance 26-30 by a 6-1 vote, extending the moratorium for an additional twelve months; the minutes record that it applies to all data centers regardless of type, size and power thresholds. [City of Kings Mountain]
Apex (Wake County): The draft minutes of the April 14, 2026 Apex Town Council meeting record a unanimous (5-0) vote approving a twelve-month moratorium (ORD-2026-034) on development applications for data centers, cryptocurrency mining, data processing and associated uses; as presented, it applies to the corporate limits, ETJ and future planning areas, taking effect April 28, 2026 and expiring April 27, 2027. [Town of Apex]
Charlotte (Mecklenburg County): Charlotte City Council approved a 150-day moratorium on applications for new telecommunications and data storage facilities on June 8, 2026, and approved an extension on October 26, 2026. The city’s FAQ says the extension expires no later than October 18, 2027, though one passage on the same page says October 1, 2027. [City of Charlotte]
Greensboro (Guilford County): On August 17, 2026, Greensboro City Council adopted a 180-day temporary development moratorium on data-center facilities with electrical power demand exceeding 10 megawatts. [City of Greensboro]
Statesville (Iredell County): The minutes of Statesville City Council’s September 14, 2026 meeting, in the October 5, 2026 agenda packet, record unanimous approval of a consent agenda that included the second reading of an ordinance imposing a 180-day moratorium on applications for new telecommunications and data centers in the city and its extraterritorial zoning jurisdiction. [City of Statesville]
Raleigh (Wake County): On October 6, 2026, Raleigh City Council approved a temporary six-month pause on acceptance and review of data-center development approvals, including Special Use Permits for major data centers; the city’s FAQ schedules the pause to end April 6, 2027. [City of Raleigh]
Mooresville (Iredell County): On November 2, 2026, the Town of Mooresville Board of Commissioners approved a 12-month moratorium on data centers that temporarily pauses the consideration of new data center development proposals. [Town of Mooresville]
Kings Mountain’s data-center page says its moratorium is scheduled to remain in effect through August 24, 2027, unless the City Council ends it earlier. The register files Kings Mountain under Cleveland County, the county of its City Hall address in the Census geocoder; the moratorium applies to the city’s jurisdiction, which this register has not mapped by county. [City of Kings Mountain; U.S. Census Bureau]
Expiry dates are stated by the record, not computed
Desk analysisWhere a record states an end date, the entries above repeat it. Where a record gives only a length, such as Statesville’s 180 days or Greensboro’s 180 days, this guide does not calculate an end date, because the effective date and any extension are set by the ordinance itself. [City of Statesville; City of Greensboro]
Records can disagree. Charlotte’s FAQ gives the extended moratorium an end of no later than October 18, 2027, but one passage on the same page says October 1, 2027, and a video transcript on the page still says the moratorium runs through November 5, 2026. Edgecombe County’s August 3 minutes, presented for approval on September 8, record the adoption, while a timeline in the same packet dates it August 6, 2026. Both readings are kept until the publisher corrects one. [City of Charlotte; Edgecombe County Board of Commissioners]
Vance County’s moratorium was scheduled to expire November 13, 2026, and the county noticed a special meeting that day to consider extending it through December 13, 2026. This register has not seen minutes of that meeting, so it does not say whether the extension passed. [Vance County Clerk to the Board]
Our analysis: a passed end date does not by itself mean a moratorium has lapsed, and a scheduled end date does not mean it will. Treat each status as the record’s statement on its date, and check the adopting body’s latest agenda before relying on it.
A statewide moratorium is a bill, not law
Desk analysisHouse Bill 1189 is titled as a two-year datacenter permitting moratorium with related study directives. At this register’s November 6, 2026 review it had been referred to the House Rules committee on May 5, 2026, and had not been enacted; this guide did not re-check its status. [North Carolina General Assembly]
Our analysis: every moratorium in this register was adopted by a county or municipal government. Pending legislation can change the local picture only if it is enacted, and its text at enactment would control.
How records get into this guide
Desk analysisA moratorium is listed only when this desk has read the adopting body’s own record: minutes, an adopted or packet ordinance, a public notice or the government’s own explanatory page. Draft minutes are labelled as drafts. Reports seen only in news coverage or third-party trackers are held back until a primary record is found. Each record keeps its own review date in the source register; records first reviewed earlier in November 2026 were not re-checked for this guide. [Vance County Board of Commissioners; Town of Apex]
Our analysis: the list is the register’s holdings, not a complete census of North Carolina’s local governments. A jurisdiction missing here may have acted without this desk having found its record.