Power & grid

Utility review, large-load obligations and the difference between an approved schedule and energized capacity.

Source review 2026-11-17

On October 6, 2026, Duke Energy Carolinas and Duke Energy Progress filed a large-load tariff settlement in NCUC Docket Nos. E-7, Sub 1329 and E-2, Sub 1380. Filing was not Commission approval. [Duke Energy Carolinas and Duke Energy Progress, filed with the N.C. Utilities Commission (copy hosted by SELC); Duke Energy]

On November 16, 2026, the NCUC issued written orders in those dockets. Duke Energy’s Form 8-K reports that the orders approve the Comprehensive Settlements and establish a DC Schedule for certain data center customers, with revised rates expected January 1, 2027. An approved schedule is not a site-specific service agreement or delivered capacity. [Duke Energy Corporation (SEC Form 8-K); Duke Energy]

Our analysis: identify the actual serving utility, controlling tariff, required network work and service agreement for a particular property. A planned campus or load request is not delivered service.

From the source brief.