DC Schedule
A rate schedule the North Carolina Utilities Commission established in its November 16, 2026 orders for certain Duke Energy data center customers.
Duke Energy’s Form 8-K reports that the Commission’s November 16, 2026 written orders in the Duke Energy Carolinas and Duke Energy Progress rate cases establish a DC Schedule applicable to certain data center customers. Duke says it is still assessing that portion of the orders and will continue to engage with customers and other stakeholders on implementation. [Duke Energy Corporation (SEC Form 8-K)]
The Duke Energy Carolinas fact sheet (Docket E-7, Sub 1329) lists the schedule’s requirements: minimum 15-year contract terms for data centers above 100 MW; minimum billing demand of 75% of contract demand; interim curtailment provisions; contribution in aid of construction (CIAC) for dedicated facilities; a letter of credit for all transmission network upgrades, with partial direct assignment of those upgrades by a methodology to be determined; liquidated damages for early termination; and a stranded generation charge requiring security posting and an additional payment at the end of the contract term, also by a methodology to be determined. [Duke Energy Carolinas (SEC Exhibit 99.1)]
The Duke Energy Progress fact sheet (Docket E-2, Sub 1380) lists the same requirements. Both say the list includes terms from the Large Load Tariff settlement and others that are incremental. [Duke Energy Progress (SEC Exhibit 99.2)]
Duke’s November 17, 2026 release describes a new rate schedule for data center customers with loads above 50 megawatts. An approved schedule is not a site-specific service agreement or delivered capacity. [Duke Energy]