A megawatt figure needs a defined basis
Desk analysisThe reviewed Maiden and Lenoir records do not disclose campus IT load. Apple’s expansion statement and Google’s operating-campus description should not be converted into a delivered MW figure. An operator’s planned or operating activity is not itself evidence of the amount of energized utility capacity. [Apple; Google]
Our analysis: preserve the unit, capacity basis, phase, source date and planned-versus-delivered state. Do not combine a utility figure with an IT-load figure or add overlapping program and campus amounts simply because the values share an MW unit.
Power service is a sequence, not a map symbol
Desk analysisDuke Energy’s Form 8-K reports NCUC written orders of November 16, 2026 establishing a DC Schedule for certain data center customers. The 8-K does not identify the actual service plan, infrastructure or energization date for a selected parcel. A nearby line or substation does not establish that property’s available capacity. [Duke Energy Corporation (SEC Form 8-K); North Carolina Utilities Commission]
Our analysis: maintain separate evidence for the request, proposed service arrangement, required facilities, conditions and actual energization. Treat a possible early service stage separately from the final load assumed in a developer’s full-buildout specification.
Water use depends on the facility and cooling design
Desk analysisN.C. DEQ publishes water-resources permitting information. That general resource does not establish a named campus’s peak demand, annual use, supplier capacity or permissions. Those questions require facility-specific records, with the source and development stage kept visible. [N.C. Department of Environmental Quality]
Our analysis: request the cooling design, peak and annual demand assumptions, supply source, utility commitments and relevant withdrawal or discharge records. Distinguish an operator’s design statement from measured operating use. If the source does not disclose an item, it remains unknown, not zero.
An approval answers a specific question
Desk analysisN.C. DEQ’s air and water resources describe environmental approval trails. Neither should be read as a universal statement that a project is built, financed, connected to utilities or operating. Local land-use authority must also be established for the actual parcel. [N.C. Department of Environmental Quality; N.C. Department of Environmental Quality]
Our analysis: identify the issuing authority, scope, conditions and date of each approval. Keep backup-generation permissions, cooling-water questions, local land use and utility service in separate diligence tracks until the record establishes how they connect.
Compare like with like and keep the gaps visible
Desk analysisOur analysis: compare the same capacity basis and development stage, and show the source trail alongside the figure. When the sources differ, state that difference rather than producing an apparently precise total. A smaller disclosed number is not necessarily a smaller completed project, and a larger marketed number is not necessarily a larger current utility customer.
The North Carolina tracker preserves those qualification fields and the comparison view presents each record’s disclosures separately. Use the source register for the original documents and the coverage matrix for unresolved fields; the desk’s selected records do not establish a complete statewide power or water denominator.