Large-load customer
A utility customer, such as a data center, whose electricity demand is large enough to trigger separate contract terms and cost protections.
Duke Energy says it had previously required data centers and other large loads of 100 megawatts or more to agree to contract terms that protect other customers from the cost of serving them. [Duke Energy]
Its October 7, 2026 release describes a settlement between Duke Energy Carolinas, Duke Energy Progress and the North Carolina Public Staff that, if approved by state regulators, would apply to all large-load customers of 50 megawatts or more with an 80% load factor that sign an electric service agreement in North Carolina after June 1, 2026. Under it, new large-load customers, including new data centers, must take service under a High Load Factor rate schedule. [Duke Energy]
The protections the release lists include a nonrefundable, upfront payment for grid facilities that serve only that customer, such as a substation, and upfront deposits and security guarantees for grid upgrades that serve all customers, such as transmission lines. [Duke Energy]
On November 16, 2026, the NCUC approved the other rate-case stipulations without modification, except the Large Load Tariff stipulation, and established a DC Schedule for certain data center customers. Duke’s fact sheets list minimum 15-year contract terms for data centers above 100 MW and minimum billing demand of 75% of contract demand. [Duke Energy Carolinas (SEC Exhibit 99.1)] [Duke Energy Progress (SEC Exhibit 99.2)]
Duke’s November 17, 2026 release describes the new schedule as applying to data center customers with loads above 50 megawatts. A customer’s size or load factor alone does not show which contract or schedule governs a particular site. [Duke Energy]