Primary-source update review for 2026-11-20. The excerpts below retain their original publication dates and are attributed to their publishers.
blog.google — 2026-11-17: “North Carolina is the tenth state to provide Google AI and digital skills training statewide at no cost” [blog.google]
Research focus: Power & grid. Utility review, large-load obligations and the difference between an approved schedule and energized capacity.
On October 6, 2026, Duke Energy Carolinas and Duke Energy Progress filed a large-load tariff settlement in NCUC Docket Nos. E-7, Sub 1329 and E-2, Sub 1380. Filing was not Commission approval. [Duke Energy Carolinas and Duke Energy Progress, filed with the N.C. Utilities Commission (copy hosted by SELC); Duke Energy]
On November 16, 2026, the NCUC issued written orders in those dockets. Duke Energy’s Form 8-K reports that the orders approve the Comprehensive Settlements and establish a DC Schedule for certain data center customers, with revised rates expected January 1, 2027. An approved schedule is not a site-specific service agreement or delivered capacity. [Duke Energy Corporation (SEC Form 8-K); Duke Energy]
Our analysis: identify the actual serving utility, controlling tariff, required network work and service agreement for a particular property. A planned campus or load request is not delivered service.
AWS North Carolina investment program — AWS announced an estimated $10 billion investment in North Carolina cloud and AI infrastructure, located in Richmond County. This program commitment is not verified completed spending. [Amazon Web Services]
The announcement anticipates at least 500 direct high-skilled jobs; construction and supply-chain jobs are different measures.
Do not add this program commitment to its associated Richmond County campus record.
AWS Richmond County campus — AWS records a Richmond County groundbreaking on October 30, 2025 and describes the campus as being built in September 2026. NC DEQ issued the site’s backup-generation and temporary bridge-power air permits on August 28, 2026. [U.S. Census Bureau; Amazon Web Services; Amazon Web Services; N.C. Department of Environmental Quality, Division of Air Quality]
NC DEQ’s August 28, 2026 release reports permits for 588 Amazon emergency backup engines and 57 Duke Energy temporary bridge-power engines. Duke’s engines must retire within one year of starting operations.
The air permits establish a dated regulatory milestone. The reviewed sources do not establish the campus’s completion, energized IT load or actual start date for bridge-power operations.
The associated $10 billion program is recorded separately; no independently verified completed campus expenditure is supplied.
Google Lenoir data center — Google identifies an operating data center in Lenoir and records that its first facility opened in 2008. [U.S. Census Bureau; Google; Google]
Google’s reported investment exceeds $4 billion across the region and state; it is not assigned here as a campus valuation.
The operator’s community and economic-impact statements do not disclose campus IT load, water allocation or current vacancies.
Disclosure discipline: a planned program is not completed expenditure; marketed IT capacity is not proof of energized utility demand. County and municipal approvals must be verified at the relevant jurisdiction. This edition does not change canonical project facts or confidence grades.