The desk's source-governed infrastructure records for this operator. Individual campuses and multi-site investment programs retain their own scope and uncertainty.

Digital Realty has 2 campus or program records in the selected North Carolina register. This count does not establish the operator’s full North Carolina footprint, operating capacity, or total investment.

Digital Realty Moores Chapel campus proposal, Charlotte
Digital Realty presented a proposed 400 MW IT campus at Moores Chapel, on 157 acres about 10 miles west of downtown Charlotte, to the City of Charlotte’s Data Center Task Force on September 17, 2026.
Digital Realty Uptown Charlotte facilities
Digital Realty operates three Uptown Charlotte buildings, at 113 and 125 N Myers Street and 731 E Trade Street, totalling about 100,000 square feet and about 2 MW of IT load in place, according to its September 17, 2026 presentation to the city’s Data Center Task Force.
North Carolina project and program records with disclosed investment, power and confidence.
Project / programOperatorLocalityInvestmentPowerConf.
Digital Realty Moores Chapel campus proposal, Charlotte
Proposed — delivery dates preliminary; presented during Charlotte’s data-center moratorium · campus · reviewed
Digital RealtyMecklenburg CountyNot disclosed in cited source400 MW IT capacity proposed — developer presentationB
Digital Realty Uptown Charlotte facilities
Operating — about 2 MW IT in place; 725 E Trade expansion planned for 2028 · campus · reviewed
Digital RealtyMecklenburg CountyNot disclosed in cited sourceAbout 2 MW IT in place; 12 MW planned at 725 E Trade — developer presentationB