Microsoft: North Carolina data-center operator.
The desk's source-governed infrastructure records for this operator. Individual campuses and multi-site investment programs retain their own scope and uncertainty.
Microsoft has 5 campus or program records in the selected North Carolina register. This count does not establish the operator’s full North Carolina footprint, operating capacity, or total investment.
- Microsoft Catawba County datacenter program
- In November 2022, Catawba County, Conover, Hickory, Maiden and the county’s economic development corporation announced Microsoft’s plan to invest at least $1 billion in the phased development of four data centers in Catawba County over 10 years.
- Microsoft Lyle Creek datacenter, Conover
- Microsoft is building a datacenter in the greater Conover area near Highway 16 in Catawba County. Its September 2026 update says the first building’s exterior is in its final stages.
- Microsoft Boyd Farms datacenter, Maiden
- Microsoft is constructing the Boyd Farms datacenter off Zeb Haynes Road in Maiden. Its May 2026 update describes progress on building foundations, underground utilities and infrastructure.
- Microsoft Hickory (Stover) datacenter
- Microsoft is building a datacenter in the greater Hickory area, near the Hickory-Lincolnton Highway in Catawba County. Its May 2026 update reports underground utilities and foundation work in progress.
- Microsoft Person County datacenter campus
- Microsoft bought 1,350 acres in Person County in October 2024 and plans a datacenter campus there. Its April 2026 update says the project is in planning, with early site preparation under way.
| Project / program | Operator | Locality | Investment | Power | Conf. |
|---|---|---|---|---|---|
| Microsoft Catawba County datacenter program Announced program — sites under construction · program · reviewed | Microsoft | Catawba County | At least $1B planned over 10 years across four data centers — local partners’ announcement | Not disclosed in cited source | B |
| Microsoft Lyle Creek datacenter, Conover Under construction — first building exterior in final stages (operator update) · campus · reviewed | Microsoft | Catawba County | Within the Catawba County program; site cost not disclosed | Not disclosed in cited source | B |
| Microsoft Boyd Farms datacenter, Maiden Under construction — foundations and underground utilities (operator update, May 2026) · campus · reviewed | Microsoft | Catawba County | Within the Catawba County program; site cost not disclosed | Not disclosed in cited source | B |
| Microsoft Hickory (Stover) datacenter Under construction — foundations and underground utilities (operator update, May 2026) · campus · reviewed | Microsoft | Catawba County | Within the Catawba County program; site cost not disclosed | Not disclosed in cited source | B |
| Microsoft Person County datacenter campus Planning — early site preparation (operator update, April 2026) · campus · reviewed | Microsoft | Person County | Not disclosed in cited source | Not disclosed in cited source | B |
Campus and multi-site program records are kept distinct. Investment and power figures are not summed across overlapping scopes.