Skip to content
  • NORTH CAROLINA AI economy SOURCE-LINKED
NorthCarolinAIResearch Desk

Printable evidence packet: Core Scientific Marble campus

Printable evidence packet for Core Scientific Marble campus: reviewed disclosures, open diligence questions, reuse qualifications and controlling sources, with a JSON download.

Core Scientific’s April 21, 2026 SEC filing describes a 65 MW critical-IT data center at 155 Palmer Lane in Marble, licensed to CoreWeave, with about 37 MW operational and billing.

campusConfidence ADesk review 2026-11-18

Exact reviewed disclosures

Operator
Core Scientific
Locality label
Cherokee County
Source-attributed status
Operating and billing — remainder was due in H1 2026 (April 2026 SEC filing)
Investment
Not disclosed in cited source
Power
65 MW critical IT; 117 MW grid capacity — SEC filing
Employment
Not disclosed in cited source

The filing describes the campus as about 73 acres being converted from cryptocurrency mining to HPC and AI workloads, with 117 MW of grid capacity and 61,440 square feet of IT whitespace. It reports 37 MW billable as of March 2026 (57% completion) and substantial completion of the rest expected in the first half of 2026; this record has not verified that completion. [Core Scientific, Inc. (SEC EDGAR)]

CoreWeave’s licensed allocation at Marble is 65 MW, with an initial 12-year term and two five-year extension options; base license fees have commenced. Construction is managed by T5 under a cost-plus contract with a guaranteed maximum price. [Core Scientific, Inc. (SEC EDGAR)]

Power comes through three contracts: 35,000 kW of firm service from Murphy Electric Power Board, a Tennessee Valley Authority distributor, running through August 30, 2029; and two Duke Energy Carolinas electric service agreements, one with 48,000 kW of contract demand and one beginning at 34,000 kW, both year to year. [Core Scientific, Inc. (SEC EDGAR)]

Core Scientific’s campus page lists 117 MW of total power capacity and a 70-acre campus footprint; the SEC filing gives about 73 acres. Neither names the county: the U.S. Census Bureau geocoder places 155 Palmer Lane, Marble in Cherokee County. [Core Scientific] [U.S. Census Bureau]

Questions the public record still needs to answer.

These are diligence prompts. General reference sources below are not verified project-specific approvals, utility agreements or incentive awards.

Land use and jurisdiction

Which parcel, legal jurisdiction and land-use approvals apply to Core Scientific Marble campus?

The reviewed locality label is “Cherokee County”. Confirm parcel jurisdiction independently. No locality-matched land-use reference is recorded in this packet; consult the actual governing jurisdiction.

Electric service

What site-specific utility service agreement, interconnection milestone and delivery date are documented?

Reviewed disclosure: 65 MW critical IT; 117 MW grid capacity — SEC filing. A campus specification is not an energized utility commitment. The general utility and Commission references do not identify the serving utility, governing rate or service agreement for this particular site.

Employment and timing

Which phase, hiring dates, job types and current employer postings are documented?

Reviewed jobs disclosure: Not disclosed in cited source. An announced target is not a live vacancy count. The operator references do not establish an employer affiliation, hiring commitment or project-specific training agreement for an unrelated training provider.

Reuse qualifications

  • This is a public research packet, not a legal, tax, engineering or investment opinion.
  • A source association is not proof of a final permit, utility commitment, incentive award or completed project.
  • Campus and multi-site program scopes are different. Do not sum overlapping program and campus investment or capacity figures.
  • Publication dates, desk review dates and project milestones have different meanings. An export is not a new source verification.
  • Unknown or undisclosed values remain unknown; locality markers are approximate and do not establish parcel jurisdiction.

Canonical record: https://northcarolinai.com/data-centers/core-scientific-marble