The presentation lists forty 10 MW data halls in two-story buildings, initial delivery expected in 2027 and the full 400 MW by the end of 2030, with closed-loop, air-cooled chillers built to support liquid cooling. It says the dates are preliminary and all information is subject to change. [City of Charlotte]
The same deck notes a Duke Energy regional requirement to take part in a power-shedding program, and says Digital Realty funds all transmission and substation upgrades. Those are the developer’s statements, not utility filings. [City of Charlotte]
The same deck asks the task force to vote on recommending that City Council extend Charlotte’s data-center moratorium, effective November 5, 2026, with the length left blank. The proposal is not a rezoning, permit or utility commitment. [City of Charlotte]