Start with the unit of analysis
Desk analysisAWS’s North Carolina announcement describes a planned investment program, while Google’s Lenoir page describes a named campus and wider regional investment. Their scopes are different. NorthCarolinAI keeps program records separate from campus records and does not add an associated program commitment to campus figures. [Amazon Web Services; Google]
Our analysis: create a record for the actual question you need to answer. Keep the operator’s name, source date, locality, record type and unresolved stage together. The selected North Carolina register is a starting point for inquiry, not a census of all facilities or proof that a listed site is operating.
Read what the operator actually discloses
Desk analysisOperator pages establish only the activity and scope they disclose. Google identifies its Lenoir facility; Apple’s August 2025 announcement describes an expansion at Maiden. A statement that construction is under way does not establish that an expansion is complete or that its full utility load has been delivered. [Google; Apple]
Our analysis: preserve the original wording and capacity basis. Record future delivery targets as targets. When a page retains an expired target but does not confirm completion, leave the stage unresolved rather than advancing it because time has passed.
Follow the locality and environmental trails separately
Desk analysisN.C. DEQ maintains distinct air and water permitting resources. Those are starting points for environmental research, rather than proof of a named campus’s approvals. An operator’s postal address is not a substitute for the parcel’s jurisdiction, and an environmental permit is not evidence that every local approval is complete. [N.C. Department of Environmental Quality; N.C. Department of Environmental Quality]
Our analysis: record the actual parcel, application or permit identifier, decision date, conditions and issuing body. Separate a pending application from an approval, an approval from construction, and construction from operation. Establish the controlling county or municipality for the property before interpreting its land-use requirements.
Build a project-specific power file
Desk analysisDuke Energy’s Form 8-K reports that on November 16, 2026 the NCUC issued written orders establishing a DC Schedule for certain data center customers in Dockets E-7, Sub 1329 and E-2, Sub 1380. An approved schedule is not a promise of capacity for any particular property. A marketed IT-load figure, a utility request and an energized service commitment are separate facts. [Duke Energy Corporation (SEC Form 8-K); North Carolina Utilities Commission]
Our analysis: ask for the applicable service plan, required infrastructure, dependencies, timing and customer obligations. Confirm the controlling tariff or order for the actual customer; a general policy summary should not be used as a rate quote or guarantee of available capacity.
Keep incentives and outcomes attributable
Desk analysisThe N.C. Department of Revenue publishes a notice concerning repeal of electricity exemptions for datacenters. A tax notice does not establish a particular buyer’s entitlement or a campus-specific award. Announced capital, equipment purchases, local tax receipts and employment remain different economic measures. [N.C. Department of Revenue]
Our analysis: attach each financial assumption to its actual agreement, scope and date. Use the source register, comparison view and downloadable data to retain the evidence trail. Where the underlying record is absent, report the item as unverified or undisclosed rather than substituting a statewide average.